一、塑石假山施工準備
First, plastic stone rockery construction preparation
1、根據施工總平麵圖,進行場地整理,暢通道路,對實地進行勘查,複核標高及與周圍建築的相互位置關係,對施工生活用水、施工用電、場內臨設用房等進行統籌合理安排。
1, according to the construction plan, site arrangement, smooth road, exploration of the field, check the elevation and the positional relationship with the surrounding architecture, construction of water, electricity, construction of temporary housing for the reasonable arrangement.

2、施工前,施工管理人員準備好安全牌、安全禁令牌以及七牌一圖、施工現場的各管理物品,及消防器材。
2, before construction, the construction management personnel ready safety card, security ban card, and seven cards, a map, the construction site of the management of goods, and fire equipment.
3、落實技術資料,在施工圖紙接到以後,立即組織有關人員熟悉施工圖,在看圖時必須抓住主要施工圖環節,盡量在施工圖紙會審得到解決,減少今後有施工時出現的設計變動,以便組織施工。
3, the implementation of technical information, after receiving the construction drawings, immediately organize relevant personnel to be familiar with construction drawings, in the picture must grasp the main construction link, to be solved in the construction drawings and design changes have reduced the construction in the future, in order to organize construction.
4、開工前,施工人員準備好施工質量評定表,施工日記等有關書麵資料及標準管理各種台帳資料。
4, before construction, the construction staff prepared the construction quality assessment form, construction diary and other relevant written materials and standards, management of various accounting data.
5、落實施工機械提高現代化施工水平。
5, the implementation of construction machinery, improve the level of modern construction.
二、塑石假山施工組織部署
Two, plastic stone rockery construction, organization and deployment
1、施工組織以假山製作安裝為主線進行施工,工作主要定位放樣、塑石假山基礎開挖、預埋件埋置、骨架焊接製作、鋼絲網片焊接製作、鋼絲網片綁紮、一層抹灰 、二層抹灰 、三層抹灰 、造型 、顏料麵油。
1, the construction organization to the production and installation of the main line of rockery construction, main positioning lofting, rockery foundation excavation, buried, embedded frame welding production, steel wire mesh, welded wire mesh, making a layer of plaster, lashing two layer, three layer plastering plastering, shape, surface oil paint.
2、各分包施工班組無條件服從施工總計劃。
2, sub contractor construction team unconditionally obey the construction master plan.
秋葵视频官网app用智慧和熱情全力為客戶生產優良的產品,您的滿意是秋葵视频官网二维码下载不懈的追求。
We use wisdom and enthusiasm to produce the best products for our customers, and your satisfaction is our unremitting pursuit.
濟南秋葵视频官网下载假山水景園林
技術支持:濟南諾商

谘詢熱線:
13064079165
在線客服